https://login.veeam.com/en/oauth?client_id=nXojRrypJ8&redirect_uri=https%3A%2F%2Fwww.veeam.com%2Fservices%2Fauthentication%2Fredirect_url&response_type=code&scope=profile&state=eyJmaW5hbFJlZGlyZWN0TG9jYXRpb24iOiJodHRwczovL3d3dy52ZWVhbS5jb20va2IxMzc2IiwiaGFzaCI6ImNiNmU3NDI0LWI5ZTUtNDFlYS1hZWExLTMxZGZjYWQ4YjE2ZiJ9
1-800-691-1991 | 9am - 8pm ET
EN

Reverse incremental job scheduling does not work properly

Challenge

Reverse incremental job starts ignoring their scheduled settings, and run on the days selected for Synthetic Fulls, even when the check-box is grayed out.

Solution

To resolve the issue you need to enable forward incremental mode in the job settings and deselect "Enable synthetic fulls" option.  You can then go back and set the job to use reverse incremental mode.  Making this adjustment should correct the behavior.
KB ID:
1376
Product:
Veeam Backup & Replication
Version:
6.0.0.153
Published:
2011-12-02
Last Modified:
2020-08-13
Please rate how helpful this article was to you:
5 out of 5 based on 1 ratings
Thank you for helping us improve!
An error occurred during voting. Please try again later.

Couldn't find what you were looking for?

Below you can submit an idea for a new knowledge base article.
Report a typo on this page:

Please select a spelling error or a typo on this page with your mouse and press CTRL + Enter to report this mistake to us. Thank you!

Spelling error in text

Knowledge base content request
By submitting, you agree that your personal data will be managed by Veeam in accordance with the Privacy Policy.
Your report was sent to the responsible team. Our representative will contact you by email you provided.
We're working on it please try again later